April 2018
Spills data for April 2018
All download files are in PDF format and open in a new window.
Date Reported | Incident Site | JIV Date | Terrain | Cause | Estimated Spill Volume (bbl) | Recovered Spill Volume (bbl) | Clean-up Status | Comments | Photo | JIV Report |
---|---|---|---|---|---|---|---|---|---|---|
Apr 04, 2018 | 8'' Isimiri-Imo Gate Pipeline at Obiakpu | Apr 10, 2018 | Land | Sabotage | 10 | 5 | Recovery completed on 19 Apr 2018, assessment completed on 01 Aug 2018, clean-up and remediation completed on 13 Apr 2019, site certified on 07 May 2021, documentation planned to be completed in Dec 2022 | - | Download | Download |
Apr 06, 2018 | 28'' Bomu-Bonny Pipeline at Patrick Waterside | Apr 07, 2018 | Land | Sabotage | 22 | n/a | Spill was contained on 07 Apr 2018, no recoverable oil found, assessment completed on 27 Jun 2018, clean-up and remediation planned to be completed in Jun 2024 | Stated timeline for cleanup is as agreed between NAPIMS, DPR,NOSDRA,BODO and community representatives; to ensure effective/thorough clean-up and certification. The Bodo clean-up process is managed by an independent mediation committee (Bodo Mediation Initiative - BMI) comprising amongst others of representatives of; Federal /State Government regulators, Bodo Community and Coalition of NGOs. | Download | Download |
Apr 07, 2018 | Imo River Well 31S 6'' Flowline at Owaza | Apr 10, 2018 | Land | Sabotage | 1 | n/a | No recoverable oil found, assessment completed on 01 Aug 2018, clean-up and remediation completed on 16 May 2019, site certified on 10 Jun 2019, documentation completed on 30 Jun 2022 | - | Download | Download |
Apr 17, 2018 | 18'' Assa- RumuekpePipeline at Ochia | Apr 20, 2018 | Land | Sabotage | 2 | n/a | No recoverable oil found, assessment completed on 28 Jun 2018, clean-up and remediation completed on 11 Apr 2019, site certified on 28 Aug 2020, documentation completed on 30 Jun 2022 | - | Download | Download |
Apr 25, 2018 | 20” Kolocreek-Rumuekpe Pipeline at Imogu-Rumuekpe | Jun 12, 2018 | Land | Sabotage | 20 | n/a | Spill was contained on 26 Apr 2018, no recoverable oil found, assessment completed on 16 Jan 2019, clean-up and remediation completed on 17 May 2020, site certified on 07 May 2021, documentation completed on 25 Jan 2022 | - | Download | Download |
Apr 25, 2018 | 20'' Kolocreek-Rumuekpe Pipeline at Odau | Jun 29, 2018 | Land | Sabotage | 605 | n/a | Spill was contained on 26 Apr 2018, recovery completed on 29 Oct 2018, assessment completed on 19 Jul 2022, clean-up and remediation not required, site certification planned to be completed in Dec 2022 | Spill volume adjusted subsequent to JIV based on additional information gained during recovery operations. | Download | Download |
Apr 26, 2018 | 24'' Trans-Ramos Pipeline at Odimodi | May 06, 2018 | Swamp | Operational | 580 | 530 | Spill was contained on 27 Apr 2018, recovery completed on 31 Jul 2018, assessment completed on 15 Oct 2018, clean-up and remediation completed on 12 Mar 2020, site certified on 07 Dec 2021, documentation planned to be completed in Jun 2022 | - | Download | Download |
Apr 26, 2018 | 24'' Trans-Ramos Pipeline at Odimodi | May 04, 2018 | Swamp | Operational | 924 | 910 | Spill was contained on 25 Apr 2018, recovery completed on 02 Aug 2018, assessment completed on 29 Sep 2018, clean-up and remediation completed on 17 Feb 2020, site certified on 07 Dec 2021, documentation completed on 26 Apr 2022 | - | Download | Download |
Apr 28, 2018 | 24'' Trans-Ramos Pipeline at Odimodi | May 05, 2018 | Swamp | Operational | 0.8 | n/a | No recoverable oil found, assessment completed on 10 Oct 2018, clean-up and remediation completed on 12 Mar 2020, site certified on 07 Dec 2021, documentation planned to be completed in Jun 2022 | - | Download | Download |
Apr 29, 2018 | 12'' Imo River - Ogale Pipeline at Umuelechi Uzuaku | May 04, 2018 | Land | Sabotage | 116 | 95 | Spill was contained on 28 Apr 2018, recovery completed on 07 May 2018, assessment completed on 05 Jul 2018, clean-up and remediation completed on 04 Feb 2019, site certified on 07 Nov 2022, documentation completed on 23 Nov 2022 | - | Download | Download |
Apr 29, 2018 | 14'' Okordia – Rumuekpe Pipeline at Ukpeliede | May 05, 2018 | Land | Sabotage | 400 | 346 | Recovery completed on 20 May 2018, assessment completed on 01 Mar 2023, clean-up and remediation not required, site certification planned to be completed in Jun 2023 | - | Download | Download |
Apr 30, 2018 | 16" Egbema to Assa Pipeline at Ekugba | May 04, 2018 | Land | Sabotage | 2 | 9 | Recovery completed on 04 May 2018, assessment completed on 18 Feb 2019, clean-up and remediation completed on 10 Apr 2019, site certified on 26 Jul 2019, documentation completed on 05 Oct 2021 | - | Download | Download |