May 2020
Spills data for May 2020
All download files are in PDF format and open in a new window.
Date Reported | Incident Site | JIV Date | Terrain | Cause | Estimated Spill Volume (bbl) | Recovered Spill Volume (bbl) | Clean-up Status | Comments | Photo | JIV Report |
---|---|---|---|---|---|---|---|---|---|---|
May 01, 2020 | 28'' Nkpoku - Bomu Pipeline at B-Dere | May 02, 2020 | Land | Sabotage | 16 | n/a | No recoverable oil found, assessment completed on 25 Aug 2021, clean-up and remediation completed on 07 Nov 2022, site certified on 24 Jan 2023, documentation completed on 31 Jan 2023 | - | Download | Download |
May 02, 2020 | 28'' Nkpoku - Bomu Pipeline at Elelenwo | May 02, 2020 | Land | Sabotage | 60 | n/a | Recovery completed on 03 May 2020, assessment completed on 11 Sep 2020, clean-up and remediation completed on 17 Jun 2021, site certified on 04 Apr 2022, documentation planned to be completed in May 2022 | - | Download | Download |
May 03, 2020 | 14” Okordia – Rumuekpe Pipelin at Edeoha | May 05, 2020 | Land | Sabotage | 8 | n/a | Spill was contained on 04 May 2020, no recoverable oil found, assessment completed on 25 Aug 2021, clean-up and remediation completed on 26 May 2022, site certified on 17 Oct 2022, documentation completed on 21 Oct 2022 | - | Download | Download |
May 03, 2020 | 16” Egbema – Assa Pipeline at Etekwuru | May 07, 2020 | Land | Sabotage | 63 | n/a | Spill was contained on 04 May 2020, recovery completed on 03 Dec 2020, assessment completed on 04 May 2023, clean-up and remediation not required, site certification planned to be completed in Sep 2023 | - | Download | Download |
May 04, 2020 | 8” Nkali – Imo River Pipeline at Odagwa | May 04, 2020 | Land | Sabotage | 1 | n/a | No recoverable oil found, assessment completed on 14 Jan 2021, clean-up and remediation planned to be completed in Dec 2022 | - | Download | Download |
May 05, 2020 | 4'' Imo River Well 55S Flowline at Igiriukwu | May 05, 2020 | Land | Sabotage | 1 | n/a | No recoverable oil found, assessment completed on 19 Feb 2021, clean-up and remediation not required, site certification planned to be completed in Mar 2022 | - | Download | Download |
May 08, 2020 | 3'' AdibawaWell 6T Flowline Flange at Edagberi-Betterland | May 12, 2020 | Land | Operational | 0.7 | n/a | No recoverable oil found, assessment completed on 25 Nov 2021, clean-up and remediation not required, site certified on 26 May 2022, documentation completed on 26 May 2022 | - | Download | Download |
May 09, 2020 | 4'' Bonny Well 10S Flowline Riser at Oloma | May 25, 2020 | Swamp | Operational | 0.1 | n/a | No recoverable oil found, assessment completed on 25 May 2020, clean-up and remediation not required, site certified on 28 Aug 2020, documentation completed on 26 Mar 2021 | - | Download | Download |
May 27, 2020 | 20" Kolocreek - Rumuekpe Pipeline at Aminigboko | May 30, 2020 | Land | Sabotage | 3 | n/a | Recovery completed on 07 Jun 2020, assessment completed on 20 Mar 2021, clean-up and remediation not required, site certified on 14 Jun 2022, documentation completed on 21 Jun 2022 | - | Download | Download |
May 28, 2020 | 4'' Kanbo Well 5L Flowline at Tunu | Jun 04, 2020 | Swamp | Sabotage | 0.03 | n/a | No recoverable oil found, assessment completed on 04 Jun 2020, clean-up and remediation not required, site certified on 10 Nov 2020, documentation completed on 26 Mar 2021 | - | Download | Download |
May 30, 2020 | 12'' ImoRiver 2 - Ogale Pipeline at KomKom | May 31, 2020 | Land | Sabotage | 2 | n/a | Recovery completed on 31 May 2020, assessment completed on 15 Sep 2021, clean-up and remediation not required, site certified on 07 Jul 2022, documentation planned to be completed in Mar 2023 | - | Download | Download |