July 2021
Spills data for July 2021
All download files are in PDF format and open in a new window.
Date Reported | Incident Site | JIV Date | Terrain | Cause | Estimated Spill Volume (bbl) | Recovered Spill Volume (bbl) | Clean-up Status | Comments | Photo | JIV Report |
---|---|---|---|---|---|---|---|---|---|---|
Jul 01, 2021 | 10'' Diebu Creek - NunRiver - Pipeline at Nangi-Ama | Jul 06, 2021 | Land | Sabotage | 267 | 251 | Recovery completed on 30 Aug 2021, assessment completed on 26 Jan 2022, clean-up and remediation not required, site certified on 16 Jan 2023, documentation planned to be completed in Jun 2023 | - | Download | Download |
Jul 06, 2021 | 4'' Imo River2 Well 21L Flowline at Odagwa | Jul 09, 2021 | Land | Sabotage | 3 | n/a | No recoverable oil found, assessment completed on 23 Nov 2022, clean-up and remediation not required, site certification planned to be completed in Aug 2023 | - | Download | Download |
Jul 07, 2021 | 14'' Okordia - Rumuekpe Pipeline at Ihuowo | Jul 09, 2021 | Land | Sabotage | 147 | 4 | Recovery completed on 11 Aug 2021, assessment completed on 24 Oct 2022, clean-up and remediation not required, site certification planned to be completed in Apr 2023 | - | Download | Download |
Jul 13, 2021 | Opukushi Well 24T Flowline at Egbemagalabiri-Agbidiama | Jul 29, 2021 | Swamp | Sabotage | 2 | 1 | Recovery completed on 03 Aug 2021, assessment completed on 28 Mar 2022, clean-up and remediation not required, site certification planned to be completed in Dec 2022 | - | Download | Download |
Jul 15, 2021 | 10" Diebu Creek - Nun River Pipeline at Eniwari-Onyoma | Jul 18, 2021 | Land | Sabotage | 59 | 55 | Recovery completed on 23 Aug 2021, assessment completed on 26 Jan 2022, clean-up and remediation not required, site certified on 16 Jan 2023, documentation planned to be completed in Jun 2023 | - | Download | Download |
Jul 16, 2021 | 36'' Rumuekpe - Nkpoku Pipeline at Ibaa | Jul 17, 2021 | Land | Sabotage | 348 | 230 | Recovery completed on 12 Oct 2021, assessment completed on 22 Dec 2022, clean-up and remediation not required, site certification planned to be completed in May 2023 | - | Download | Download |
Jul 17, 2021 | NunRiver 3'' Well 13T Flowline at Oporoma | Jul 22, 2021 | Land | Operational | 0.1 | n/a | No recoverable oil found, assessment completed on 19 Nov 2021, clean-up and remediation completed on 18 Oct 2022, site certified on 04 May 2023, documentation planned to be completed in Jun 2023 | - | Download | Download |
Jul 17, 2021 | 14'' Okordia-Rumuekpe Pipeline at Ihuowo | Jul 19, 2021 | Land | Sabotage | 81 | 1 | Recovery completed on 11 Sep 2021, assessment completed on 25 Sep 2023, clean-up and remediation not required, site certified on 25 Sep 2023, documentation completed on 16 Oct 2023 | - | Download | Download |
Jul 18, 2021 | 20'' Kolocreeck-Rumuekpe Pipeline at Odau KP8 | Jul 18, 2021 | Swamp | Sabotage | 198 | 190 | Recovery completed on 05 Oct 2021, assessment completed on 19 Jul 2022, clean-up and remediation not required, site certification planned to be completed in Dec 2022 | - | Download | Download |
Jul 21, 2021 | 14'' Okordia-Rumuekpe Pipeline at Akara-Olu | Jul 23, 2021 | Swamp | Sabotage | 15 | 11 | Recovery completed on 11 Sep 2021, assessment completed on 11 May 2022, clean-up and remediation not required, site certification planned to be completed in Nov 2023 | - | Download | Download |
Jul 25, 2021 | 20'' Kolocreek - Rumuekpe Pipeline at Okoma | Jul 27, 2021 | Swamp | Sabotage | 12 | 10 | Recovery completed on 08 Nov 2021, assessment completed on 25 Mar 2024, clean-up and remediation not required, site certification planned to be completed in Jun 2024 | - | Download | Download |
Jul 27, 2021 | 4'' ImoRiver Well 4T Flowline at Owaza | Jul 31, 2021 | Land | Sabotage | 6 | 3 | Recovery completed on 03 Aug 2021, assessment completed on 12 May 2022, clean-up and remediation not required, site certified on 18 Apr 2023, documentation completed on 30 Jun 2023 | - | Download | Download |
Jul 27, 2021 | 20" Kolocreek-Rumuekpe Pipeline at Okporowo | Jul 30, 2021 | Land | Sabotage | 2 | 1 | Recovery completed on 20 Sep 2021, assessment completed on 06 Sep 2022, clean-up and remediation not required, site certified on 26 Jun 2023, documentation completed on 06 Jul 2023 | - | Download | Download |
Jul 27, 2021 | 20'' Kolocreek - Rumuekpe Pieline at Ihuowo | Jul 29, 2021 | Land | Sabotage | 25 | 20 | Recovery completed on 20 Sep 2021, assessment completed on 27 Oct 2022, clean-up and remediation not required, site certified on 26 Jun 2023, documentation planned to be completed in Aug 2023 | - | Download | Download |
Jul 30, 2021 | 16'' NunRiver Kolocreek T/L RoW at KP 3-6 | Aug 06, 2021 | Swamp | Sabotage | 40 | 5 | Spill was contained on 25 Aug 2021, recovery completed on 30 Aug 2021, assessment completed on 28 Mar 2022, clean-up and remediation not required, site certified on 16 Jan 2023, documentation completed on 28 Apr 2023 | - | Download | Download |